LRT train carriage. Photo: LRT Jakarta
Fachri Audhia Hafiez • 27 November 2025 16:03
Jakarta: Construction on the Jakarta LRT Phase 1B project has reached 80.57 percent completion as of the second week of November 2025. Rawamangun Station is one of the projects progressing rapidly.
The most advanced station is Rawamangun Station, at 91.69 percent, said Jakarta LRT Project Director Ramdani Akbar in North Jakarta, as quoted by Antara on Wednesday, November 26, 2025.
Furthermore, construction of the viaduct, or railway bridge, has reached 95.40 percent completion. Furthermore, construction of the Pramuka BPKP Station is 65.29 percent complete, Pasar Pramuka Station (45.24 percent), Matraman Station (65.89 percent), and Manggarai Station (30.42 percent).
Regarding the proposed extension of the Jakarta LRT Phase 1C route connecting Manggarai to Dukuh Atas and Phase 2A to Jakarta International Stadium (JIS), although this is still being discussed with the Jakarta Provincial Government (Pemprov DKI Jakarta), Ramdani stated, "Jakpro is still discussing with the DKI Jakarta Provincial Government which will be implemented first."
Ramdani also spoke about the planned development of a new Jakarta LRT line to the north. He revealed that PT Jakarta Propertindo (Jakpro) already has a Jakarta LRT study covering the route to Manggarai, JIS, Dukuh Atas, and Halim Perdanakusuma. However, the connection to PIK is still being studied.
Previously, Jakarta Governor Pramono Anung revealed that the development of the new LRT line will connect Kelapa Gading to Pantai Indah Kapuk (PIK) 2.